Which of the following procedures would an entity most likely include in its disaster recovery plan?
参考答案(由小熊题库网聘请的专业题库老师提供的解答)
请点击↑↑↑ 查看官方参考答案 按钮
习题解析
请点击 查看官方参考答案 按钮
您可能感兴趣的题目
1 .The performance audit report of an information technology department indicated that the department lacked a disaster recovery plan. Which of the following steps should management take first to correct this condition?
A Bulletproof the information security architecture. B Prepare a statement of responsibilities for tasks included in a disaster recovery plan. C Designate a cold site. D Designate a hot site.
2 .An information technology director collected the names and locations of key vendors, current hardware configuration, names of team members, and an alternative processing location. What is the director most likely preparing?
A Disaster recovery plan. B System security policy. C System hardware policy. D Data restoration plan.
3 .A controller is developing a disaster recovery plan for a corporation's computer systems. In the event of a disaster that makes the company's facilities unusable, the controller has arranged for the use of an alternate location and the delivery of duplicate computer hardware to this alternate location. Which of the following recovery plans would best describe this arrangement?
A Hot spare site agreement. B Hot site. C Back-up site procedures. D Cold site.
4 .Bacchus, Inc. is a large multinational corporation with various business units around the world. After a fire destroyed the corporate headquarters and largest manufacturing site, plans for which of the following would help Bacchus ensure a timely recovery?
A Daily backup. B Network security. C Backup power. D Business continuity.
5 .Which of the following best describes a hot site?
A Location that is equipped with the necessary hardware and possibly software. B Location where a company can install data processing equipment on short notice. C Location that is considered too close to a potential disaster area. D Location within the company that is most vulnerable to a disaster.
7 .A client is concerned that a power outage or disaster could impair the computer hardware's ability to function as designed. The client desires off-site backup hardware facilities that are fully configured and ready to operate within several hours. The client most likely should consider a:
A Cool site. B Hot site. C Warm site. D Cold site.
8 .Which method of backup involves copying only the data items that have changed since the last backup?
A Off-schedule. B Full. C Differential. D Incremental.
9 .Which of the following terms refers to a site that has been identified and maintained by the organization as a data processing disaster recovery site but has not been stocked with equipment?
A Hot. B Cold. C Flying start. D Warm.
10 .Which of the following procedures would an entity most likely include in its computer disaster recovery plan?
A Translate data for storage purposes with a cryptographic secret code. B Develop an auxiliary power supply to provide uninterrupted electricity. C Maintain a listing of all entity passwords with the network manager. D Store duplicate copies of critical files in a location away from the computer cen...