1 .某工程双代号网络计划如下图所示,图中已标出各项工作的最早开始时间和最迟开始时间,该计划表明( )。

A 工作1-3的自由时差为零 B 工作2-4的自由时差为2 C 工作2-5为关键工作 D 工作3-5的总时差为零 E 工作4-6的总时差为2

题型: 多选题 提问时间: 2021-08-23

2 .某工程双代号网络计划如下图所示,图中已标出的各个节点的最早时间和最迟时间,该计划表明( )。

A 工作1-2的自由时差为2 B 工作2-5的总时差为7 C 工作3-4为关键工作 D 工作3-5为关键工作 E 工作4-6的总时差为零

题型: 多选题 提问时间: 2021-08-23

3 .

A $11 B $12 C $14 D $15

题型: 单选题 提问时间: 2021-08-23

4 .A company uses an overhead absorption rate of $3·50 per machine hour, based on 32,000budgeted machine hours for the period. During the same period the actual total overheadexpenditure amounted to $108,875 and 30,000 machine hours were recorded on actualproduction.By how much was the total overhead under or over absorbed for the period?

A Under absorbed by $3,875 B Under absorbed by $7,000 C Over absorbed by $3,875 D Over absorbed by $7,000

题型: 单选题 提问时间: 2021-08-23

5 .A cost centre has an overhead absorption rate of $4·25 per machine hour, based on a budgetedactivity level of 12,400 machine hours.In the period covered by the budget, actual machine hours worked were 2% more than thebudgeted hours and the actual overhead expenditure incurred in the cost centre was $56,389.What was the total over or under absorption of overheads in the cost centre for theperiod?

A $1,054 over absorbed B $2,635 under absorbed C $3,689 over absorbed D $3,689 under absorbed

题型: 单选题 提问时间: 2021-08-23

7 .

A $10 B $11 C $12 D $13

题型: 单选题 提问时间: 2021-08-23

8 .A manufacturing company uses a machine hour rate to absorb production overheads, whichwere budgeted to be $130,500 for 9,000 machine hours. Actual overheads incurred were$128,480 and 8,800 machine hours were recorded.What was the total under absorption of production overheads?

A $880 B $900 C $2,020 D $2,900

题型: 单选题 提问时间: 2021-08-23

9 .Which of the following would NOT be classified as a service cost centre in amanufacturing company?

A Product inspection department B Materials handling department C Maintenance department D Stores