[单选题] 提问人:匿名网友 提问时间:2021-08-24

关于项目决策和工程造价的关系,下列说法中错误的是( )。


A .项目决策的正确性是工程造价合理性的前提
B .项目决策的内容是决定工程造价的基础
C .项目决策的广度影响投资估算的精确度
D .工程造价的数额影响项目决策的结果

提问人:匿名网友 提问时间:2021-08-24

参考答案(由小熊题库网聘请的专业题库老师提供的解答)

请点击↑↑↑ 查看官方参考答案 按钮

习题解析

请点击 查看官方参考答案 按钮

您可能感兴趣的题目


1 .Which one of the following is most likely to be the explanation for an adverse materialusage variance?

A A major supplier of material has reduced the rate of trade discount B Rates of pay have been increased C Quality standards have been increased D Unforeseen material price rises have been incurred

题型: 单选题 提问时间: 2021-08-24

2 .Which one of the following is most likely to be the reason for a favourable labourefficiency variance?

A An ideal standard was used as part of a quality improvement programme B A shortage of skilled staff meant that more trainees had been recruited C Lower grade material was purchased D Staff have recently been trained in material handling techniques

题型: 单选题 提问时间: 2021-08-24

3 .Nujig Co reduced its quality specification for raw materials. The lower quality of materialsmeant that a batch of products had to be reworked.What is the most likely effect on the variances for materials usage and labour efficiency?

A Materials usage Adverse;Labour efficiency Adverse B Materials usage Adverse;Labour efficiency Favourable C Materials usage Favourable;Labour efficiency Adverse D Materials usage Favourable;Labour efficiency Favourable

题型: 单选题 提问时间: 2021-08-24

4 .The standard direct material cost per unit for a product is calculated as follows:10·5 litres at $2·50 per litreLast month the actual price paid for 12,000 litres of material used was 4% above standard andthe direct material usage variance was $1,815 favourable. No inventory of material is held.What was the adverse direct material price variance for last month?

A $1,000 B $1,200 C $1,212 D $1,260

题型: 单选题 提问时间: 2021-08-24

5 .A company operating a standard costing system has the following direct labour standards perunit for one of its products:4 hours at $12·50 per hourLast month when 2,195 units of the product were manufactured, the actual direct labour costfor the 9,200 hours worked was $110,750.What was the direct labour rate variance for last month?

A $4,250 favourable B $4,250 adverse C $5,250 favourable D $5,250 adverse

题型: 单选题 提问时间: 2021-08-24

7 .一般情况下,确定某个建设项目的具体地址,需要经过建设地区选择和建设地点选择两个不同的工作阶段,它们两者之间是一种( )。

A 互补关系 B 依托关系 C 递进关系 D 互斥关系

题型: 单选题 提问时间: 2021-08-24

8 .当工业集聚带来的( )的总和超过生产集聚带来的利益时,综合经济效益反而下降。

A “外部不经济性” B “外部不协调性” C “内部不经济性” D “内部不协调性”

题型: 单选题 提问时间: 2021-08-24

9 .投资设想阶段投资估算的精确度的要求为:允许误差大于±( )%。

A 5 B 10 C 25 D 30

题型: 单选题 提问时间: 2021-08-24

10 .某地拟于2013年兴建一座工厂,年生产某种产品50万吨。已知2010年在另一地区已建类似工厂,年生产同类产品30万吨,投资5.43亿元。若综合调整系数为1.5,用单位生产能力估算法计算拟建项目的投资额应为( )亿元。

A 6.03 B 9.05 C 13.58 D 18.10

题型: 单选题 提问时间: 2021-08-24

 
如有问题 请联系客服