[单选题] 提问人:匿名网友 提问时间:2021-08-23

Beanie’s master budget shows that the planned activity level for next year is expected to be50,000 machine hours. At this level of activity, the following manufacturing overhead costsare expected: $Factory supervision 300,000Machine supplies 80,000Indirect materials 70,000Depreciation on factory building 50,000What total manufacturing overhead costs should be included in a flexible budget for alevel of activity of 60,000 machine hours?


A .$504,000
B .$530,000
C .$540,000
D .$600,000

提问人:匿名网友 提问时间:2021-08-23

参考答案(由小熊题库网聘请的专业题库老师提供的解答)

请点击↑↑↑ 查看官方参考答案 按钮

习题解析

请点击 查看官方参考答案 按钮

您可能感兴趣的题目


1 .企业的开办费,可以在开始经营之日的当年一次性扣除,也可以按照新税法有关长期待摊费用的处理规定处理并可改变。(  )

Y 对 N 错

题型: 判断题 提问时间: 2021-08-23

2 .企业投资性房地产计提的减值准备,可以在税前扣除。(  )

Y 对 N 错

题型: 判断题 提问时间: 2021-08-23

3 .母子公司各自作为独立的纳税人分别纳税。(  )

Y 对 N 错

题型: 判断题 提问时间: 2021-08-23

4 .Which of the following statements relating to a fixed budget is correct?

A Should never be prepared as it has no purpose B Is useful in evaluating a manager’s performance by comparing actual costs againstplanned costs C Shows planned results at the original budgeted activity level D Is changed only if the actual level of activity is different than originally budgeted

题型: 单选题 提问时间: 2021-08-23

5 .What is the primary difference between a fixed budget and a flexible budget?

A A fixed budget contains only fixed costs, while a flexible budget also containsvariable costs B A fixed budget reflects different activity levels, while a flexible budget is preparedfor a single level of activity C A fixed budget is prepared for a single level of activity, while a flexible budget ...

题型: 单选题 提问时间: 2021-08-23

7 .Rickety prepared a 2012 budget for 90,000 units of product. Actual production in 2012 was100,000 units. Actual production in 2011 was 97,000 units. The company has now prepareda 2013 budget for 90,000 units.To be most useful, with what amounts should the actual results for 2012 be compared ina performance report?

A The original budget for 90,000 units B The original budget flexed to 100,000 units C Last year’s actual results for 97,000 units D The 2013 budget for 90,000 units

题型: 单选题 提问时间: 2021-08-23

8 .Starry prepared a fixed budget of 50,000 direct labour hours, with estimated variableoverhead costs of $250,000 and fixed overhead cost of $60,000. It then prepared a flexiblebudget at 38,000 labour hours.What is the total overhead cost in the flexible budget?

A $190,000 B $247,000 C $250,000 D $260,000

题型: 单选题 提问时间: 2021-08-23

9 .Umni’s budgeted manufacturing costs for 25,000 units are:Fixed costs $25,000 per monthVariable costs $300,000Next month Umni expects to produce only 21,000 units as an additional national holiday hasbeen declared.What is the flexible budget for total manufacturing costs for next month?

A $260,000 B $252,000 C $277,000 D $325,000

题型: 单选题 提问时间: 2021-08-23

10 .Wacky uses a flexible budgeting system. At normal capacity of 10,000 units budgetedmanufacturing overheads are $50,000 variable and $135,000 fixed. Last month Wacky’sactual overhead costs totalled $187,500 for 11,000 units produced.What is the difference between the actual and budgeted costs?

A $2,500 unfavorable B $2,500 favorable C $4,500 unfavorable D $6,000 favorable

题型: 单选题 提问时间: 2021-08-23

 